Long Island preparatory works start end-2026 on 570 ha off Bedok

HDB said on 30 June 2026 that preparatory works for Long Island start from end-2026, in a first phase of about 570 ha west of Bedok Jetty.

Swee Homes Newsroom. Published 14 November 2026, 6:00 pm.

A smiling father and his teenage son stand with fishing rods on a sandy beach, with palm trees behind them and a crane barge beyond an orange barrier far offshore. Swee Homes.

Does anything change at East Coast Park from end-2026?

Does anything change for you at East Coast Park when the works start? HDB said on 30 June 2026 that preparatory works for Long Island start from end-2026, in waters at least 130m from the shoreline. Beaches stay open for near-shore swimming, and exercise paths stay open for jogging and cycling. The works take place in the waters off the East Coast, and sea users are advised to keep a safe distance.

The release describes Long Island as Singapore's large-scale critical coastal protection strategy. HDB is the appointed reclamation agent, and the Urban Redevelopment Authority (URA) also reiterated the Government's commitment to continue engaging stakeholders before finalising reclamation plans. The preparatory works are the near-term part. The main reclamation works come later, and the release gives them no date.

What changed on 30 June 2026

The release sets out what the preparatory works are. It describes Long Island as a critical coastal protection measure to safeguard lives and livelihoods, as rising sea levels increasingly affect low-lying coastal areas, including Singapore's East Coast. Given the scale of the project, it says, preparatory works are essential to lay the groundwork for the future land reclamation.

The works primarily involve the removal of seabed obstructions, followed by the construction of temporary sand bunds and sand infilling. They will be clearly demarcated by silt screens and/or floating barriers. The release is careful on one point: the area used for preparatory works is not reflective of the future land profile of Long Island. That profile is still to be refined through technical studies and public engagement.

The works are done in phases, and the table sets them side by side.

The two phases of preparatory works, as the release describes them
First phaseSecond phase
WhereWaters west of Bedok JettyWaters east of Bedok Jetty
Area (hectares)About 570About 155
ShapeAbout 7km east to west, up to 1km wide north to southNot given in the release
StartEnd-2026After the water sports and sporting events, including the SEA Games 2029

Source: HDB, release of 30 June 2026, paragraphs 4 and 5.

Who is affected, and who is not

The release is specific about who feels what. Beach and path users keep access. Members of the public can continue to use the beaches along East Coast Park throughout the preparatory works. Sea users are advised to keep a safe distance from the marine vessels and from the designated work area, which will be cordoned off for public safety. Safety advisories will be put up at East Coast Park and on agencies' websites.

A smiling father and his young daughter wade hand in hand in calm shallow water near a sandy beach, with other swimmers nearby and a crane barge beyond an orange barrier. Swee Homes.

Sea sports users are affected. The release says some will be displaced because sea space along the East Coast is reduced. Kiteboarding is the most affected, with minor to moderate impact on other sea sport users. The release says the impact will be mitigated by phasing the works, and agencies will work with affected users to explore alternative sites in the sea space to the east of Bedok Jetty in the interim, and elsewhere in Singapore.

The Environmental Study, which HDB commissioned, covers the rest. It is summarised in the table below.

What the Environmental Study found, as the release lists it
TopicFindingRelated measure or statement in the release
Water qualityNo significant changes; water quality will continue to meet the prevailing marine water quality criteriaNo measure named in this item
Currents and wavesSlight localised changes near Bedok Jetty, which are expected to have minimal impact on existing water-based activitiesNear-shore activities such as swimming can continue along the entire stretch of the East Coast
Visual and air qualityUp to minor visual and ambient air quality impact from sand infilling, with intermittent sediment plumes and dustSilt screens deployed to contain sediment plumes; dust levels closely monitored
BiodiversityUp to minor impact on some terrestrial and marine biodiversity; some coral and seagrass beds near the site may experience short-term, localised impact from sediment plumesNo measure named in this item; the majority of coral and seagrass nearby, including Sisters' Island Marine Park, is described as largely unaffected
Sea sportsSome users displaced as sea space along East Coast is reduced; kiteboarding most affected, minor to moderate impact on other usersImpact will be mitigated by the phasing of works; agencies to explore alternative sites with affected users

Source: HDB, release of 30 June 2026, paragraph 8.

The release says the majority of coral and seagrass in the vicinity, including Sisters' Island Marine Park, is largely unaffected. It also says some coral and seagrass beds near the site may experience short-term and localised impact from sediment plumes.

What the numbers show

Two areas are given. The first phase covers approximately 570 ha, and spans around 7km from east to west and up to 1km wide from north to south. The second phase covers approximately 155 ha.

A young man and woman lean on a seaside railing looking out at a barge inside an orange floating barrier, with open water and other boats around it. Swee Homes.
Area of each phase of preparatory works
PhaseArea (hectares)
First phase, west of Bedok Jettyabout 570
Second phase, east of Bedok Jettyabout 155

Source: HDB, release of 30 June 2026.

Adding the two gives 725 ha, and the first phase is larger by 415 ha. Both are arithmetic on two approximate figures, worked out by Swee Homes, and the release prints neither. The first phase is also the one with a start date. The second phase will only commence after the completion of these events, including the SEA Games in 2029. The reason given is the continued use of part of the sea space fronting East Coast Park for water sports and major international sporting events.

Per the release, the Environmental Study report was available for public feedback for four weeks from 30 June 2026. The release says agencies will thoroughly evaluate the feedback received and incorporate suitable suggestions before finalising the mitigation measures that will be adopted.

What this means for you

Take three illustrative users of the East Coast. User A swims or jogs at the park. User B kiteboards. User C takes a boat or board out near the works. These are examples, and the terms are the release's own.

Three smiling kiteboarders in wetsuits stand on a beach beside a board and a wooden rack of packed kites. Swee Homes.
Illustrative East Coast users and what the release says for each
Illustrative userWhat the release says
Illustrative user A: a swimmer or jogger at East Coast ParkBeaches remain open for near-shore swimming, and all exercise paths and tracks remain accessible for jogging and cycling
Illustrative user B: a kiteboarderKiteboarding is the most affected sea sport; agencies to explore alternative sites east of Bedok Jetty in the interim, and elsewhere in Singapore
Illustrative user C: a boat or board user near the worksKeep a safe distance from the marine vessels and the cordoned off work area

Source: Users are illustrations. Terms are from HDB, release of 30 June 2026, paragraphs 6 and 8.

The release says safety advisories will be put up at East Coast Park and on agencies' websites, and the release points to go.gov.sg/long-island for more information. If you use the sea, keep a safe distance from vessels and the cordoned off area.

The exception is kiteboarding. If you kiteboard, the release says kiteboarding is the most affected sea sport, and the interim alternative it names is the sea space to the east of Bedok Jetty. It names no long-term site: the release says agencies will explore sites, and none is confirmed.

On visual and air quality, the release says up to minor impact from sand infilling operations is expected, with intermittent sediment plumes and dust. Silt screens will be deployed to contain the plumes and dust levels will be closely monitored. An Environmental Monitoring and Management Plan (EMMP) will track water quality, suspended sediment levels, noise and dust throughout the works.

Swee Homes' take

Read this release as two stories. The first is the preparatory works, with a start date, an area and a list of effects. The second is Long Island itself, which the release says will span a few decades and has no reclamation date. In Swee Homes' view, mixing the two leads to confusion about what is happening now and what is not.

The sentence worth remembering is that the area used for preparatory works is not reflective of the future land profile. In Swee Homes' view, a reader who sees 570 ha and 7km and pictures the final shape is reading more into the release than it says.

A second point is about tone. The release names the people who lose something, in plain words: kiteboarding is the most affected. In Swee Homes' view, naming the group is a good habit in a public release, and it makes the interim measure easier to test later.

This article offers no view on nearby property, because the release says nothing about it.

What to watch next

The release gives dated markers. The first phase starts in end-2026. The next phase of public engagement begins from end-2026 as well, drawing on ideas gathered from more than 14,000 people to date. It will invite Singaporeans and stakeholders to explore key topics, including potential recreational activities along the new coastline and within the future reservoir. The second phase of preparatory works waits until after events including the SEA Games in 2029.

The main reclamation works will commence only after the agencies have completed the relevant technical studies, determined mitigation measures, and reviewed and incorporated feedback from further public engagements. The technical studies are expected to be completed over the next few years. The release gives no date for the main works.

To sum up: the works are offshore, the beaches stay open, and sea sports users are the group to watch. For the national picture of households and population, see the Swee Homes guide on Singapore's population and households.

Go deeper

About the figures

Figures from HDB's news release 'Preparatory Works for Long Island Project to Commence from End-2026', published 30 June 2026, read on 19 October 2026. The sum and the difference of the two areas are worked out by Swee Homes. General information, not financial advice.

Sources: HDB and URA news release, 30 June 2026, read 14 November 2026.

To report an error, write to hello@sweehomes.com. The newsroom checks it against the source and shows any correction at the top of the story with its date.