HDB's 16 April 2026 release brings Keppel's centralised cooling to 12 Tengah BTO projects, with the option to subscribe left to each household.
- approximately 14,000households across 12 BTO projects with access to the system
- up to 30%less energy than conventional air-conditioning, HDB says
- 20-yearterm of each Keppel contract

Do you have to use Tengah's centralised cooling?
No. HDB's release of 16 April 2026 says homebuyers in Tengah have the option of subscribing to the Centralised Cooling System (CCS). Its Annex says air-conditioner ledges are provided in all flats in Tengah for those who prefer their own system.
The release adds that HDB has awarded Keppel a contract to supply chilled water to nine more Tengah BTO projects. It gives no subscription price. So the practical question is not whether the system exists, but whether you want to subscribe, on terms the release leaves to Keppel.
What changed
HDB has awarded Keppel Ltd.'s Infrastructure Division a chilled water supply contract to design, install and operate CCS at nine upcoming BTO projects in Tengah. Under this 20-year contract, approximately 10,000 households in Tengah's Brickland, Park and Forest Hill districts can engage Keppel to provide chilled water to cool their homes.

This is Keppel's second CCS contract for Tengah BTO projects. The first, awarded in September 2024, covers three projects over 20 years. With the new award, HDB says approximately 14,000 households across 12 BTO projects in Tengah will have access.
| Contract | Date | BTO projects | Households with access | Term |
|---|---|---|---|---|
| First | Awarded September 2024 | 3 (Brickland Weave, Plantation Verge and a Plantation Edge project with a two-part name in HDB's list) | About 4,000 (worked out by Swee Homes) | 20 years |
| Second | Announced 16 April 2026 | 9 (in Brickland, Park and Forest Hill districts) | Approximately 10,000 | 20 years |
| Together | 12 | Approximately 14,000 |
Source: HDB, news release of 16 April 2026. The first contract's household figure is Swee Homes arithmetic: 14,000 less 10,000.
HDB describes how it works. Chilled water is piped to homes from centralised chillers, so flats do not need individual condensers. HDB says the CCS uses up to 30% less energy than conventional air-conditioning systems, and that residents who subscribe early can have air-conditioning ready on key collection.
When completed, the CCS at the 12 projects will connect to Keppel's Operations Nerve Centre for remote control and real-time performance monitoring. The release says the centre uses AI and machine learning to support predictive maintenance and optimise plant performance. The Cooling Studio at HDB Hub in Toa Payoh has a full-scale mock-up of a typical home unit; Keppel's website has virtual tours and price plans.
HDB frames the award as part of its commitment to realise Tengah as Singapore's first and largest smart and sustainable HDB town. Keppel says the system delivers chilled water from high-efficiency chiller plants and is designed for long-term reliability and efficiency. Within the flats, it says it will optimise the design and placement of the chilled water pipes, taking interior aesthetics into account where feasible and giving residents flexibility in planning their home layout.
Who is affected, and who is not
The households affected are those in the nine new projects, which the release does not name, and those in the three projects of the first contract. It places the nine in Brickland, Park and Forest Hill. It gives no key collection or completion date for them.
Within those projects the effect is a choice. Annex A says Keppel manages the sign-ups, design, installation, operation and maintenance, and handles the contractual arrangements with residents. HDB says it is not a party to Keppel's contract with subscribers, so a subscriber's agreement is with Keppel.
Who is not covered? A household in a Tengah project outside the two contracts is not described by this release. A household that prefers its own air-conditioning is covered by the ledge provision, not by the subscription. HDB's role is to plan and build the developments and, with Keppel, to provide CCS-ready infrastructure such as strengthened roofs or plant areas, electricity for the plant, and risers for the chilled water pipes.
| Party | What Annex A says it does |
|---|---|
| HDB | Plans and builds the BTO developments and schedules works for installing, testing and commissioning; with Keppel, provides CCS-ready infrastructure; provides air-conditioner ledges in all flats in Tengah |
| Keppel | Manages sign-ups, design, installation, project management, operation and maintenance; markets the CCS; handles contractual arrangements with residents |
| A household | Can subscribe to the CCS or prefer its own air-conditioning system |
Source: HDB, news release of 16 April 2026, Annex A.
What the numbers show
The release gives the second contract and the total, not the first contract's households. Worked out by Swee Homes, the first contract covers about 4,000 households, from 14,000 less 10,000. That is arithmetic on two approximate figures, so treat it as a rough size and not as an HDB number.
| Contract | BTO projects |
|---|---|
| First contract, September 2024 | 3 |
| Second contract, announced 16 April 2026 | 9 |
| Both contracts together | 12 |
Source: HDB, news release of 16 April 2026.
Source: HDB, news release of 16 April 2026.
The chart shows the second contract is three times the project count of the first: nine projects, against three.
The energy figure needs a careful reading. HDB says up to 30% less energy than conventional air-conditioning systems. The release does not say how it was measured, and it gives no figure for what a household would save. Keppel's own statement lists benefits such as potential cost savings from lower upfront equipment costs and reduced maintenance requirements, and the release gives no number for any of them.
What this means for you
Here is an illustrative comparison. Household A and Household B are both in a Tengah project covered by a CCS contract. They are not real households.

| Illustrative case | What the release and its Annex say applies |
|---|---|
| Illustrative: Household A subscribes to the CCS | Chilled water is piped from centralised chillers, with no individual condenser; the agreement is with Keppel, not HDB |
| Illustrative: Household B prefers its own air-conditioning system | Air-conditioner ledges are provided in all flats in Tengah |
| Illustrative: either household | The release gives no subscription price, so a household compares price plans with Keppel directly |
Source: Swee Homes illustration of HDB's release and Annex A. The two households are not real.
A small worked example shows how to read the 30%. Suppose a conventional system uses ten units of electricity over a period. The words up to 30% less mean the CCS would use at least 7 units for the same cooling, worked out as ten less 30% of ten. The release gives no actual units, so this is a reading aid and not a measured result.
Four rules follow.
- Ask what the up to 30% is measured against. The release says conventional air-conditioning systems and nothing more.
- Compare price plans with Keppel directly, since the release leaves them to Keppel.
- Read the agreement as a contract with Keppel. HDB says it is not a party to it.
- Check your flat type's plan for where the pipes run. The release says Keppel will optimise the placement of chilled water pipes where feasible and gives no route.
The exception: if you already plan to fit your own air-conditioner and keep it, the ledge provision covers you and the subscription questions do not apply.
Swee Homes' take
Swee Homes' view is that centralised cooling is a service you subscribe to, closer to a utility than a fitting. A fitting is something you buy once and forget. A service has a provider and a price plan, so the questions are the ones you would ask of any service.

Three of those questions the release does not answer. What does it cost each month? What does a household commit to, and for how long? What happens when the flat changes hands? These are not complaints about the release, which is mainly about the award. They are the parts to settle before you decide.
The early-subscription point is worth a note. HDB says residents who subscribe early can have air-conditioning ready on key collection. That is convenient, and convenience is a fair reason to choose a service. Just make sure it is the reason you are choosing it for.
A reasonable person can go either way. Keppel says the service means lower upfront equipment costs, and a managed system may suit some households. Someone who prefers owning and maintaining their own units may prefer the ledge. The release supports both choices, which is itself the useful message.
What to watch next
Four things would add detail. The names of the nine projects. Their key collection dates. Keppel's price plans, which the release points readers to Keppel for. And the CCS operating from the Operations Nerve Centre once the 12 projects are completed.
To sum up: the CCS is optional, the contract is with Keppel, HDB gives no price, and the energy claim is a ceiling against conventional systems. For how a BTO exercise works before you reach the cooling question, start with the BTO exercise basics guide.
Go deeper
About the figures
Figures from HDB's news release 'HDB Awards New Centralised Cooling System Contract to Keppel for Nine BTO projects in Tengah', published 16 April 2026, and its Annex A. The first contract's household figure of about 4,000 is arithmetic by Swee Homes from HDB's approximate figures of 14,000 and 10,000. The ten-unit example is an illustration of how to read HDB's up to 30% and is not a measured result. Each source and the day it was read are listed below. General information, not financial advice.
Sources: HDB news release, 16 April 2026, read 14 November 2026; HDB news release, 16 April 2026, Annex A, read 14 November 2026.
To report an error, write to hello@sweehomes.com. The newsroom checks it against the source and shows any correction at the top of the story with its date.